Request for Information (RFI) Template


Construction Request for Information (RFI) Template in Excel

Download here:request-for-information-template-rfi (xls)

Preview:

RECOMMEND THE LETTERHEAD OF THE CONTRACTOR BE PLACED HERE
EXAMPLE ONLY
 
Request for Information / Template  
Date of RFI Submission Tuesday Nov 15, 2016
Project Example Project
Address Street Address
City and State / Zip
Request for Information RFI # ( usually the job number + RFI # )
RFI Title Brief title for the RFI ( ie: Depth of footing )
RFI Description Based upon the current design depth of the footings it appears that the overall foundation depth will not be adequate to comply with the Buidling Code of a minimum of 42 inches below grade. Please advise throughout the foundaiton plan.
RFI Resolution Date Date necessary for resolution of the RFI
Ramifications of Delay
in Resolution If this RFI is not resolved by the noted Resolution Date, it will be necessary to add temporary cold weather protection to the implementation of the foundation
( The following section to be filled out by the responsible party for the answer )
RFI Resolution All footings shall be lowered 1.5 feet throughout the structural foundation plan for the project as noted on the revised S-1 foundation plan dated Nov 17, 2016 / all reinforcement to be lengthened accordingly to accommodate this revision
Date of Resolution Nov. 17, 2016
Party responsible who ever resolved the RFI
for Resolution ( in this case the Structural Engineer )
Comments / not intended to be a part of the RFI formatted above
Once this RFI is addressed and answered, the resultant impact of the answer should
be submitted as a Change Order Request to the responsible party
The Change Order Request should parallel this RFI with its verbage and numbering
scheme to allow easy access and management of this RFI answer
The Contractor should not proceed with any contractual revisions as required by
an answered RFI until a formal and signed Change Order has been issued by the
responsible party
FAILURE TO FOLLOW THIS PROCEDURE WILL PLACE THE CONTRACTOR AT RISK
FOR ANY COSTS INCURRED DUE TO ADDED SCOPE OF WORK AS A RESULT OF THIS
REQUEST FOR INFORMATION AND THE ANSWER AS NOTED ABOVE