Download Excel Spreadsheet here:Analytical Estimating
Sample Data:
| ANALYTICAL ESTIMATING | ||||||||||
| COST MATRIX | ||||||||||
| Estimate Template for Multi Family Projects ( Basic Template – must be customized for individual project ) | ||||||||||
| First you must setup a cost matrix for the project / this cost matrix can be developed and modified as needed | ||||||||||
| The cost matrix is an analysis of basic unit costs that are developed through | ||||||||||
| experience and research /this matrix must be developed based upon the region | ||||||||||
| of the country that the project is being constructed as well as the specifics for each project | ||||||||||
| This is a cost matrix example, for the New England Areas ( these values must be researched and customized ) | ||||||||||
| Costs are shown as an example ONLY / experience and research is required to establish precision with unit values | ||||||||||
| Specialty costs such as specialty piles, sheathing , etc. – must be added, based upon specific project requirements | ||||||||||
| This cost matrix is intended to provide a basic, ball park estimate, of where the pricing should fall. It is mandatory | ||||||||||
| that individual subcontractors are involved, to verify all projections and identify the values in a more precise manner. | ||||||||||
| Example of | ||||||||||
| Spec Section | Description | Unit | Estimated | |||||||
| customized per job | Unit Value | |||||||||
| 1000 | General Conditions | |||||||||
| Project Manager | week | $2,500.00 | ||||||||
| Gen Conditions are totally dependent upon the specific project / in some cases the larger projects do not require the amount of management that some specialty projects may require | Project Engineer | week | $1,750.00 | |||||||
| Assistant Project Manager | week | $2,000.00 | ||||||||
| Asistant Project Engineer | week | $1,500.00 | ||||||||
| Field secretary or assistant | week | $1,250.00 | ||||||||
| Field office | month | $750.00 | ||||||||
| Office supplies | month | $250.00 | ||||||||
| Temporary heat | month | $250.00 | ||||||||
| Temprorary power | month | $350.00 | ||||||||
| Temporary sanitary | month | $500.00 | ||||||||
| Daily cleanup | day | $275.00 | ||||||||
| Dumpsters | each | $750.00 | ||||||||
| Documents | LS | $5,000.00 | ||||||||
| Punchlist | LS | $7,500.00 | ||||||||
| 2000 | Demolition / Sitework | |||||||||
| This activity can basically control the entire estimate / The necessity of the specific conditions and the type of land and soils will control the total cost of this division / it is important to incorporate a local subcontractor to work together with you, as you develop this divisions cost and the specifics of this division / Underpinning, sheathing, dewatering,pile driving, erosion control, etc. are all very important elements of this division and will drive the final cost of this project / Special insurances for underpinning, blasting, etc. must be considered and carefully analyzed within this Division | Tree protection | each | $250.00 | |||||||
| Haybale installation | each | $10.00 | ||||||||
| General Demolition | SF | $1.25 | ||||||||
| Specified Demolition | SF | $0.50 | ||||||||
| Demolition cleanup | day | $500.00 | ||||||||
| Demolition dumpsters | each | $750.00 | ||||||||
| Demolition cleanup | day | $500.00 | ||||||||
| Storm line | lf | $60.00 | ||||||||
| Sanitary line | lf | $85.00 | ||||||||
| utility trenching | lf | $75.00 | ||||||||
| General site grubbing | SF | $0.25 | ||||||||
| General site cut | SF | $0.15 | ||||||||
| Foundation excavation | cyds | $15.00 | ||||||||
| General site backfill | cyds | $12.00 | ||||||||
| Foundation backfill | cyds | $17.00 | ||||||||
| Perimeter drainage | lf | $12.00 | ||||||||
| Site rough grade | SF | $0.50 | ||||||||
| Site final grade | SF | $0.35 | ||||||||
| Flatwork prep | SF | $1.25 | ||||||||
| Asphalt prep | SF | $0.75 | ||||||||
| Curbs | LF | $8.00 | ||||||||
| Asphalt work | SF | $5.00 | ||||||||
| Piles | ( project specific ) | each | $2,500.00 | |||||||
| Blasting | ||||||||||
| Sheathing | ( project specific ) | SF | $20.00 | |||||||
| Underpinning | ||||||||||
| Dewatering ( project specific ) | day | $500.00 | ||||||||
| Landscaping | LS | sub value | ||||||||
| 3000 | Concrete | |||||||||
| Not as specifically important to the successful abilty to associate costs with the specific project as the sitework divison / unit values normally are more acurate for this Division / still recommend a sub | Reinforcing bar and wire | lbs | $2.00 | |||||||
| Footing concrete | cyd | $275.00 | ||||||||
| Pier concrete | cyd | $375.00 | ||||||||
| Column concrete | cyd | $550.00 | ||||||||
| Foundation wall | cyd | $375.00 | ||||||||
| Slab on grade | cyd | $325.00 | ||||||||
| Elevated slab | cyd | $450.00 | ||||||||
| Sidewalk flatwork | SF | $12.00 | ||||||||
| Pavement flatwork | SF | $8.00 | ||||||||
| Pads / misc concrete | cyds | $750.00 | ||||||||
| Site concrete / headwalls etc | cyds | $750.00 | ||||||||
| 4000 | Masonry | |||||||||
| Unit prices normally will provide a generally accurate pricing structure for this Division / Analytical estimating is normally accurate for this Division | Block | 6″ | each | $8.00 | ||||||
| 8″ | each | $12.00 | ||||||||
| 10″ | each | $14.00 | ||||||||
| 12″ | each | $16.00 | ||||||||
| Brick | common | each | $3.00 | |||||||
| special | each | $5.00 | ||||||||
| Precast | LF | $25.00 | ||||||||
| Reinforcing bar | lbs | $2.00 | ||||||||
| Mortar | cyd | $500.00 | ||||||||
| Grout | cyd | $350.00 | ||||||||
| 5000 | Structural and Misc. Metal | |||||||||
| Must involve a subcontractor / not due to an unspecific scope / needed due to difficulty in valuing structural steel | Structural steel | ton | $2,500.00 | |||||||
| Metal decking | SF | $2.00 | ||||||||
| Handrail | lf | $45.00 | ||||||||
| Stairs | riser | $175.00 | ||||||||
| Misc clips ( project specific ) | each | $25.00 | ||||||||
| Platforms ( project specific ) | SF | $35.00 | ||||||||
| Primer for steel | ton | $500.00 | ||||||||
| Shear studs | each | $5.00 | ||||||||
| 6000 | Carpentry | |||||||||
| Division that can be estimated based upon an analytical analysis / recommend the input of a local carpentry sub | Rough framing labor | SF | $6.00 | |||||||
| Rough framing material | SF | $7.00 | ||||||||
| Rough framing material | board ft | $1.25 | ||||||||
| Trim material / wood | LF | $7.50 | ||||||||
| Interior trim labor | SF | $3.00 | ||||||||
| Interior trim material | SF | $3.00 | ||||||||
| Exterior doors / labor | each | $250.00 | ||||||||
| Interior doors / labor | each | $150.00 | ||||||||
| Kitchen cabinets / labor & material | LF | $500.00 | ||||||||
| Bathroom vanity | each | $750.00 | ||||||||
| Closet shelves and poles | each | $150.00 | ||||||||
| 7000 | Thermal and Moisture protection | |||||||||
| Division that can be estimated based upon an analytical analysis / recommend the input of a local roofing sub | Foundation waterproofing | SF | $3.00 | |||||||
| Flatwork waterproofing | SF | $7.50 | ||||||||
| Fiberglass dimensional shingles | SF | $4.00 | ||||||||
| EPDM | SF | $8.00 | ||||||||
| Flashings | LF | $5.00 | ||||||||
| EIFS | SF | $15.00 | ||||||||
| Fiberglass insulation | SF | $1.50 | ||||||||
| Spray insulation | SF | $2.50 | ||||||||
| 8000 | Doors / windows | |||||||||
| Division can be estimated based upon an analytical analysis / incorporate a building material supplier | Interior doors | each | $250.00 | |||||||
| Windows | each | $450.00 | ||||||||
| General glazing | SF | $45.00 | ||||||||
| Interior glazing | SF | $25.00 | ||||||||
| Hardware / exterior doors | each | $250.00 | ||||||||
| Hardware / interior doors | each | $75.00 | ||||||||
| Garage doors | each | $2,500.00 | ||||||||
| Specialty rolling doors ( project specific ) | each | $7,500.00 | ||||||||
| 9000 | Finishes | |||||||||
| Division can be estimated based upon an analytical analysis / incorporate separate small subs for each Finish section | Flooring | wood | SF | $8.00 | ||||||
| granite | SF | $25.00 | ||||||||
| ceramic tile | SF | $12.00 | ||||||||
| carpet | SF | $3.00 | ||||||||
| vinyl | SF | $4.00 | ||||||||
| Painting | interior | SF | $1.25 | |||||||
| exterior | SF | $1.75 | ||||||||
| trim | SF | $0.75 | ||||||||
| doors | each | $75.00 | ||||||||
| Blinds | each | $125.00 | ||||||||
| 10000 | Specialties | |||||||||
| Division is normally not that influencial on the total estimate / analytical analysis will be adequate | ( project specific ) | Must research and price all specific | ||||||||
| Specialties required on the project | ||||||||||
| corridor grab rails | lf | $35.00 | ||||||||
| specialty handicap supports | each | $75.00 | ||||||||
| specialty grab bars | lf | $35.00 | ||||||||
| 12000 | Furnishings | |||||||||
| Division can be estimated based upon an analytical analysis | Kitchen appliances | Refrigerator | each | $1,500.00 | ||||||
| Stoves | each | $750.00 | ||||||||
| Microwave | each | $450.00 | ||||||||
| Fume hood | each | $250.00 | ||||||||
| Dishwasher | each | $500.00 | ||||||||
| Garbage disposal | each | $275.00 | ||||||||
| 14000 | Conveying systems | |||||||||
| Specialty Division requires a subcontractor pricing | ||||||||||
| Elevators | stop | $25,000.00 | ||||||||
| Escalator | sub contractor | |||||||||
| Handicap lifts | LF | $1,500.00 | ||||||||
| 15000 | Mechanical | |||||||||
| Division requires a local subcontractor to estimate this Division / highly competitive Division / should not be difficult to obtain proposals | Storm piping | lf | $25.00 | |||||||
| Sanitary piping | lf | $25.00 | ||||||||
| Gas piping | lf | $20.00 | ||||||||
| Water piping | lf | $15.00 | ||||||||
| Water heater | each | $2,500.00 | ||||||||
| Boiler | each | $15,000.00 | ||||||||
| Gas hot water heater | each | $2,500.00 | ||||||||
| Ductwork | LF | $15.00 | ||||||||
| RTU’s | each | $25,000.00 | ||||||||
| Toilets | each | $1,750.00 | ||||||||
| Kitchen sinks | each | $1,500.00 | ||||||||
| Bathroom sinks | each | $750.00 | ||||||||
| janitors sinks | each | $1,250.00 | ||||||||
| Shower with tub | each | $2,250.00 | ||||||||
| 16000 | Electrical | |||||||||
| Division requires a local subcontractor to estimate this Division / highly competitive Division / should not be difficult to obtain proposals | Service | sub contractor | ||||||||
| primary | ||||||||||
| secondary | ||||||||||
| Duplex outlet | each | $125.00 | ||||||||
| GFI outlet | each | $175.00 | ||||||||
| Light switch | each | $150.00 | ||||||||
| Standard flourescent light fixture | each | $350.00 | ||||||||
| Specialty light fixtures | each | $450.00 | ||||||||
| Emergency generator | sub contractor | |||||||||
| Data distribution | sf | $0.75 | ||||||||
| Security systems | sf | $1.50 | ||||||||
| Fire alarm | sf | $1.00 | ||||||||
| tie in to appliances | each | $275.00 | ||||||||
| Added costs and financial considerations | ||||||||||
| Totally dependent upon the specific project and the specific requirements of the Owner | Insurance Costs | Specialty | ||||||||
| Bond Costs | ||||||||||
| Building Permit costs | ||||||||||
| Specialty zoning fees | ||||||||||
| EPA ( Environmental Protection Agency ) specialty fees | ||||||||||
| Certification fees | ||||||||||
| Liscensing fees | ||||||||||
| It is vitally important that this COST MATRIX be constantly updated and modified as more unit values become | ||||||||||
| available | ||||||||||
| It is the estimators job to ensure that this cost matrix remain valid and current with the marketplace | ||||||||||
| Do not become complacent with unit values / the intent of this entire methodology is to enable the estimator to | ||||||||||
| present relatively accurate and timely estimates for multipe projects. | ||||||||||
| The final proposal for the project must be a refinement of this Sample Estimate and not simply the initial | ||||||||||
| ballpark presentation. | ||||||||||